Pool Project Timeline
 
Archive of Feb-April work progress. Link to images is here and link to videos is here.
  •   2/6: Old pool & deck demolition started.
  •   2/9: Poor soil & old pool shallow end ground fill needed to be dug out and replaced.
  • 2/20: Gravel bed laid, main drains, skimmers, gunite backing installed.
  • 2/22: Rebar installed.
  • 2/27: Gunite shell installed. ~28 day curing process needed. 
  • 3/12: Trenching for piping.
  • 3/18: Rear walk removed & piping base installed.
  • 3/20: Majority of piping in place. Pump room plumbing later.
  • 3/25: Waterline tile install started.
  • 3/26: Gunite @ 28 days since install.
  • 3/28: Waterline tiles grouted.
  • 3/29: Step edge tiles installed.
  • 4/1: 5 feet depth tile line installed. Gravel backfilling of piping
  • 4/5: Coping install, old equipment removal, water fill piping
  • 4/6: Coping install continued
  • 4/8: Copings grouted4/11: Concrete cut back for expansion joint
  • 4/18: Grading, caulking, 2 return outlets added
  • 4/19: Water heater removed
  • 4/24: Gravel base, concrete forms, drains, electrical bonding
  • 4/25: Concrete Day 1 pour, pump room equipment & piping hookup
  • 4/26: Concrete Day 2 deck complete, stanchions for handrail/ladders, float line anchors, shell prep for plaster
  • 4/27: Saw cut control joints, self leveling expansion joint caulking
  • 4/29: Pool plastered, filled, circulation & filtering started
  • 4/29+: Plaster start-up procedure (few weeks)