The Commons at Cedar
 
 
 
Welcome
Home
Our Community
Location
 
For Owners
Board of Managers
Documents
Social
Event RSVP
Committees
Site Search
What's New
 
Contact Management
 

 
Pool Project Timeline
 
Archive of Feb-June work progress. Link to images is here and link to videos is here.
 
  2/6: Old pool & deck demolition started.
  2/9: Poor soil & old pool shallow end ground fill needed to be dug out and replaced.
2/20: Gravel bed laid, main drains, skimmers, gunite backing installed.
2/22: Rebar installed.
2/27: Gunite shell installed. ~28 day curing process needed. 
3/12: Trenching for piping.
3/18: Rear walk removed & piping base installed.
3/20: Majority of piping in place. Pump room plumbing later.
3/25: Waterline tile install started.
3/26: Gunite @ 28 days since install.
3/28: Waterline tiles grouted.
3/29: Step edge tiles installed.
4/1: 5 feet depth tile line installed. Gravel backfilling of piping
4/5: Coping install, old equipment removal, water fill piping
4/6: Coping install continued
4/8: Copings grouted4/11: Concrete cut back for expansion joint
4/18: Grading, caulking, 2 return outlets added
4/19: Water heater removed
4/24: Gravel base, concrete forms, drains, electrical bonding
4/25: Concrete Day 1 pour, pump room equipment & piping hookup
4/26: Concrete Day 2 deck complete, stanchions for handrail/ladders, float line anchors, shell prep for plaster
4/27: Saw cut control joints, self leveling expansion joint caulking
4/29: Pool plastered, filled, circulation & filtering started
4/29+: Plaster start-up procedure (few weeks)
5/25+: Temporary chlorine/acid pumps set up and manually running until final tanks and equipment available
5/27: 28 Day plaster start-up cure time met
6/16: Fencing & gate(s) ~90% done
6/20: Chlorine tanks & pad
6/25: Prep for new lawn (sod) at back of deck
6/26: Restoration to west fence area started
6/27: Sod installed
6/28: Seed & straw front area
7/3: Chemical Controller mounted, some pool fixtures installed
7/8: Fill line spout installed, chemical tanks & tubing color coded, chlorine tanks strapped to wall, flow meter installed
7/15: Emergency power off switch in pool area and service outlet installed
7/16: Clubhouse water heater wired 
7/18: Electrical inspection for power off switch, service outlet & clubhouse hot water heater
7/21: Enclosure for chlorine tanks installed
7/22: Entrance gate installed, fence bottom gaps reduced
7/23: Flow meter & controller probe line hookup, Inspection, water condition adjusted