* Paving Project Update *
Posted on Oct 22nd, 2016

As of today (10/22) we are still scheduled to start asphalt reclaimation & paving on 10/31. Below is the present schedule for site work prior to 10/31.
  • Drainage work in back of Bldg 9 is complete except for lawn restoration.
  • 10/22 Bldg 10 landings
  • 10/24 Removal of main asphalt walk in front of Bldg 10
  • 10/25 Paving of Bldg 10 main walk
  • 10/25 Installation of new light posts for Bldg 10 & 11
  • 10/26 Belgium block curbing installation at various locations
Scheduling of this work is very dependent on weather conditions. Check back here for future updates.