Project Update 11/5
Posted on Nov 5th, 2016
Below is the status of the work as of Saturday 11/5.
- Paving has been completed in the Phase 1 area and vehicles may now park there. Be aware that when work starts in Phase 2 on 11/7 that vehicles from Phase 1 will not be able to travel in and out of the site during the day.
- Some clean up and minor landscaping is still taking place in Phase 1.
- Walkways in the Knightsbridge area are now being worked on in preparation for paving next week.