Project Update 11/12
Posted on Nov 12th, 2016
Below is the project status as of Saturday 11/12 4:00PM:
- Knightsbridge and Squires Gate are now open for all traffic and parking. This area will remain open until 7AM Monday morning. At that time, all vehicles in Knightsbridge from the clubhouse to Cedar Avenue, will have to be moved to an alternate location to make room for construction. Also, at that time, any vehicles in Squires Gate and lower Knightsbridge that you plan to use during the day will have to be moved to an alternate location to avoid being blocked. Be advised that you may not be able to return until Tuesday.
- Phase 2 (Downing Place) is planned to start on Tuesday 11/15 7AM. All vehicles on Downing Place must be moved by then. There should be sufficient visitor space parking in lower Knightsbridge and Squires Gate. Spaces in the upper part of Knightsbridge may be taken up by equipment and not available for parking.