Project Update 11/18
Posted on Nov 18th, 2016
Below is the project status at the end of today's work:
- Asphalt binder course has been put down from building 2 - 5. The main entrance section is unpaved but passable for traffic on Knightsbridge down to Squires Gate.
- Weekend parking in Downing Place is TBD and both entrances to Downing Place are blocked off. If parking is later allowed there will be no space markings and residents will have to park as best they can.
- Paving will continue on Monday 11/21, weather dependent, and all vehicles on Downing Place if allowed in this weekend would have to vacate by 7AM Monday.
- There is a possibility some paving may have to continue into Tuesday.
- Residents are advised that when the main entrance receives it's top asphalt layer, travel in and out of the site via Knightsbridge will be prohibited for a few hours. We will try to identify when this will be so that you may plan your day.