*Project Update 7/8
Posted on Jul 8th, 2016

Drainage work in front and between Buildings 13 & 14 is completed at this time. The following work is expected to be taking place during the next few weeks (order and priority is subject to change):
  • Shed and dumpster area demolition and new bases installed.
  • Various catch basin and manhole repairs.
  • Drainage work to left and rear of Building 14.
  • Building 10 walks, concrete steps, Uni-lock installation.
  • Belgium block curbing in some areas.
  • Remove asphalt on various walks and prep with Item 4 base.
As of today we do not expect asphalt reclaimation to begin before the last week of July. We will notify residents when more definitive dates are known.