Paving Project Update
Posted on Sep 20th, 2016
The concrete pad for the dumpster was poured on 9/20. We expect the new shed to be delivered on Thursday 9/22. For the remainder of this week, work should be progressing to catch basin replacements and manhole cover repairs. Building 10 walkways may begin the week of 9/26. At this time we are still projecting an early to mid-October time frame for asphalt reclaimation and repaving.
The 9/13 handout delivered to all units and mailed to off site owners can be viewed ->