Restriping Update
Posted on Sep 25th, 2018
The first half of the site (Day 1 lower section) has been completed. Rain has delayed continuation until tentatively Thursday 9/27 dependent on asphalt surfaces being dry. The remainder (Day 2) of the site affected parking spaces are described in the notice in the News article below. Presently we expect that parking spaces will need to be vacated by 11AM on Thursday morning. We will do a phone call out and post here on Wednesday with either a confirmation of the restriping taking place Thursday or a revision to the schedule.
It takes about 2 hours for the paint to dry in non-humid conditions. Call outs will be made when vehicles can be returned to their parking areas. Please remember that workers are within and along the roadways and their safety is a priority. Also, although paint is dry in one area, it may not be possible to allow access right away if a freshly painted area is at risk of being driven over. We thank everyone for their continued cooperation and patience.